TL;DR
Wallonia ordered Google to suspend construction of a building at its planned data centre in Farciennes, saying the three-hectare structure lacked proper planning permission. Google says work is paused while it awaits further guidance; the company has challenged a related permit refusal, with a court hearing scheduled for January.
Wallonia’s regional authorities have ordered Google to stop construction on a building at its planned data centre in Farciennes, Belgium, saying the three-hectare structure lacked proper planning permission. Google says it has paused work while awaiting further guidance. The dispute puts the project’s construction and proposed cooling arrangements under scrutiny, though the order applies to the building at issue rather than the entire former mining site.
A regional official told AFP that inspectors visited the site on Thursday and instructed Google representatives to halt construction. Nicolas Yernaux, a spokesperson for Wallonia’s regional authorities, described the building as a “major offense” because it had been constructed without the required permission. The order was reported by AFP on November 27; the full written order was not available online in the source material.
The permit dispute is tied to a proposed change in how the facility would be cooled. According to AFP, the original plan called for air cooling, while Google later applied to use water drawn from the nearby River Sambre. Walloon authorities rejected that application over the summer. AFP reported that concerns about severe drought conditions since spring contributed to opposition to taking water from the river. The reports provided no estimate of the amount the data centre would use.
Google has challenged the refusal in court, and AFP reported that a hearing is scheduled for January. The company told the BBC it had paused work in Farciennes “pending additional guidance” and said it remained “committed to complying with local laws.” Greenpeace Belgium separately alleged that construction continued after the relevant permission was revoked. That is the campaign group’s account; it is not, on the information available, a court finding.
Stop-work order · court hearing pending
How a cooling plan became a stop-work order
At the heart of the row is water: how the computers are cooled, and where the water comes from.
- The planAir coolingThe original project planned to cool the computers with air, Belgian media reported.
- The changeRiver waterGoogle applied to cool the site with water from the nearby River Sambre.
- SummerRequest refusedAfter a dry spring, regional officials refused the change. Google went to court.
- This weekStop-work orderInspectors told Google to halt building. Officials call it a major offence.
- NextCourt in JanuaryGoogle says it paused the works and will follow local laws.
- Blue: the former mining site, some 50 hectares.
- Orange: the building of three hectares that officials say lacks proper permission.
Sources: AFP, as published by Arab News, November 27, 2026; BBC News, November 29, 2026. Schematic.
Graphic: Powered by Thorsten Meyer AI
Permit Dispute Puts Cooling Plans at Risk
The case shows how local planning decisions can delay data centre construction, even as demand for computing capacity grows. A halt at one building does not establish that the entire Farciennes project has been suspended, but it creates uncertainty over the schedule and over what changes, if any, Google must make before work can resume.
The cooling proposal brings water use and drought concerns into the permitting dispute. Data centres need to remove heat from their computing equipment, but the available reporting does not state how much water Google sought to draw or whether an alternative cooling plan is being considered. That missing information limits what can be concluded about the project’s local water impact.
For nearby residents, the case concerns how a major development is approved and monitored. For construction contractors and suppliers, a stop-work instruction can interrupt work on the affected building. Companies relying on cloud or AI services may also watch for possible delays to new capacity, although the source material does not quantify any effect on Google’s services or customers.
Popular right now

Dyson V8 Cordless Vacuum

Vitamix 5200 Blender with 64 oz. Container, Black

Dreame G10 Pro Wet-Dry Vacuum Mop
As an affiliate, we earn on qualifying purchases.
How the Farciennes Permit Dispute Developed
The proposed facility is on a former mining site of about 50 hectares in Farciennes, in southern Belgium. The building named in the authorities’ account covers three hectares. The distinction matters: the reported order concerns that building, not a confirmed shutdown of the full site.
According to AFP, Google sought to revise its original air-cooling plan to use water from the Sambre. Regional authorities refused the application over the summer. Greenpeace Belgium said in a report released this week that drone footage showed work continuing and that the latest version of the planning permission had been revoked in August. Regional officials subsequently ordered work to stop, according to the reports.
The dispute comes amid wider scrutiny of data centre construction and resource use. The BBC described a growing backlash over the energy demands of data centres. AFP also reported that Finnish authorities halted work on two Google data centre sites in October. Those developments provide context, but they do not establish that the Belgian order is part of a coordinated action or that the circumstances in Finland are the same.
“We have operated in Belgium for over 15 years and remain committed to complying with local laws.”
— Google, in a statement reported by the BBC
Legal Status and Water Use Remain Open
The precise legal status of the building remains unresolved. Wallonia says it was built without the required permission, while Google has challenged the refusal of its application in court. The available source material does not include the written stop-work order or a court decision, and it does not establish whether the building could later be approved or altered.
It is also unclear whether Google continued construction after the regional instruction. Greenpeace said it had evidence that work was continuing before the order; Google later said it had paused the works. The reporting does not provide a later independent site inspection to reconcile those accounts. Nor does it specify the requested water volume, the final cooling design, or what conditions would allow construction to restart.
January Hearing May Clarify the Permit
The next reported milestone is the court hearing scheduled for January on Google’s challenge to the regional refusal. The hearing may clarify the status of the proposed permit change, but the available reports do not say when a decision is expected or whether the case directly determines the separate stop-work instruction.
Until then, Google says work is paused pending additional guidance, and the regional order remains the latest reported direction for the building. Further updates from the authorities, the court, or Google could clarify whether the project can proceed under its original plans, requires a different cooling arrangement, or needs additional planning approval.
Key Questions
Why did Wallonia order Google to stop construction?
Regional authorities said a three-hectare building lacked proper planning permission. A regional spokesperson described the construction as a major offense, according to AFP.
Has Google stopped all work at the Farciennes site?
The reported order concerns the building at issue, not a confirmed shutdown of the entire former mining site. Google told the BBC it had paused the works pending additional guidance.
What does the River Sambre have to do with the dispute?
Google applied to change the planned cooling system from air cooling to one using water from the River Sambre. Regional authorities refused the application over the summer; reports cite drought concerns but do not state the requested water volume.
What happens next in the legal dispute?
AFP reported that Google has challenged the permit refusal and that a court hearing is scheduled for January. The timing of any ruling and its effect on construction have not been reported.